Job milestones
10 active jobs · 32 tracked milestones · as of Mon, Sep 14
4Overduepast due and not marked complete
0Off trackflagged by the office
1Due within 21 daysnot yet complete
0Completeof 32 tracked
Needs attention
- 8/21/2026Edina · 24 days overdue · LDs per MnDOT 1807 Table 1807.1-1Overdue
- 8/28/2026Brainerd · 17 days overdueOverdue
- 8/31/2026Henning · 14 days overdue · $2,500/day LDOverdue
- 9/1/2026Moorhead · 13 days overdue · $2,500/day LD · per MnDOT 1807 Table 1807.1-1Overdue
Coming up next 45 days
- 10/1/2026Moorhead · in 17 days · $2,500/day LD · per MnDOT 1807 Table 1807.1-1Not reviewed
- 10/15/2026Moorhead · in 31 days · $2,500/day LD · per MnDOT 1807 Table 1807.1-1Not reviewed
- 10/16/2026Brainerd · in 32 days · $2,190/day LDNot reviewed
Timeline
Diamonds are contract milestones · bars are phases and no-work windows · hover for details, click to open the jobJob
Aug 2026
Sep
Oct
Nov
Dec
Jan 2027
Feb
Mar
Apr
May
Jun
Jul
Aug
Henning1 overdue
Phase 1 area substantially completeHenning
Due Aug 31, 2026 · 14 days ago
Overdue · $2,500/day LDPhase 2 area substantially completeHenning
Due Oct 30, 2026 · in 46 days
Not reviewed · $2,500/day LDAll water distribution work incl. testing completeHenning
Due Aug 1, 2027 · in 321 days
Not reviewed · $2,500/day LD2 ▸
Due Aug 31, 2026 · 14 days ago
Overdue · $2,500/day LDPhase 2 area substantially completeHenning
Due Oct 30, 2026 · in 46 days
Not reviewed · $2,500/day LDAll water distribution work incl. testing completeHenning
Due Aug 1, 2027 · in 321 days
Not reviewed · $2,500/day LD2 ▸
WillmarNext: Milestone 4 — all work except final wearing course · 11/27/2026
Moorhead1 overdue
28th St S + Partridge Creek utilities & street substantially completeMoorhead
Due Sep 1, 2026 · 13 days ago
Overdue · $2,500/day LD · per MnDOT 1807 Table 1807.1-1All other remaining work substantially completeMoorhead
Due Oct 1, 2026 · in 17 days
Not reviewed · $2,500/day LD · per MnDOT 1807 Table 1807.1-1Fully complete — turf established, punch list closedMoorhead
Due Oct 15, 2026 · in 31 days
Not reviewed · $2,500/day LD · per MnDOT 1807 Table 1807.1-1
Due Sep 1, 2026 · 13 days ago
Overdue · $2,500/day LD · per MnDOT 1807 Table 1807.1-1All other remaining work substantially completeMoorhead
Due Oct 1, 2026 · in 17 days
Not reviewed · $2,500/day LD · per MnDOT 1807 Table 1807.1-1Fully complete — turf established, punch list closedMoorhead
Due Oct 15, 2026 · in 31 days
Not reviewed · $2,500/day LD · per MnDOT 1807 Table 1807.1-1
Edina1 overdue
Milestone 6 — Cornelia Drive intersection substantially complete & open to trafficEdina
Due Aug 21, 2026 · 24 days ago
Overdue · LDs per MnDOT 1807 Table 1807.1-1Substantial CompletionEdina
Due Oct 31, 2026 · in 47 days
Not reviewed · LDs per MnDOT 1807 Table 1807.1-1 (~$2,500/day, verify)Ready for final paymentEdina
Due May 31, 2027 · in 259 days
Not reviewed · LDs per MnDOT 1807 Table 1807.1-1
Due Aug 21, 2026 · 24 days ago
Overdue · LDs per MnDOT 1807 Table 1807.1-1Substantial CompletionEdina
Due Oct 31, 2026 · in 47 days
Not reviewed · LDs per MnDOT 1807 Table 1807.1-1 (~$2,500/day, verify)Ready for final paymentEdina
Due May 31, 2027 · in 259 days
Not reviewed · LDs per MnDOT 1807 Table 1807.1-1
Brainerd1 overdue
Fergus FallsNext: Milestone 1 — all work except final wearing course · 10/31/2026
Milestone 1 — all work except final wearing courseFergus Falls
Due Oct 31, 2026 · in 47 days
Not reviewed · $1,000/day LDSubstantial CompletionFergus Falls
Due Jun 1, 2027 · in 260 days
Not reviewed · $1,200/day LDReady for final paymentFergus Falls
Due Jul 1, 2027 · in 290 days
Not reviewed · $1,200/day LD
Due Oct 31, 2026 · in 47 days
Not reviewed · $1,000/day LDSubstantial CompletionFergus Falls
Due Jun 1, 2027 · in 260 days
Not reviewed · $1,200/day LDReady for final paymentFergus Falls
Due Jul 1, 2027 · in 290 days
Not reviewed · $1,200/day LD
Eden PrairieNext: Milestone 1 — Phases 1 & 2 complete · 6/15/2027
Jobs
$33,770,094 under contractPrior Lake · #1155
Northwood Road Area Street & Utility Improvements — Phase 1
Contract dates not loaded yet — nine contract milestones.
PM Mike Holasek (VP) · $6,600,000
Henning · #1162
2026 Utility & Surface Improvements
Next: Phase 1 area substantially complete · 8/31/2026 (14 days overdue)
0 done1 overdue0 on track4 not reviewed
PM Troy Ouverson · $6,662,565
Willmar · #1160
4th Street SW Improvement Project
Next: Milestone 4 — all work except final wearing course · 11/27/2026 (in 74 days)
0 done0 on track3 not reviewed
$4,680,000
Moorhead · #1157
Partridge Creek Addition Street & Utility Improvements, Stormwater Pond and 28th St S Improvements
Next: 28th St S + Partridge Creek utilities & street substantially complete · 9/1/2026 (13 days overdue)
0 done1 overdue0 on track2 not reviewed
PM Troy Ouverson / Orry Wiechmann · $3,860,794
Brooklyn Center
City of Brooklyn Center
Contract dates not loaded yet — upload the Agreement/Special Provisions.
PM Mike Holasek (VP) · $3,450,000
Edina · #1161
West 72nd Street Improvements (Cornelia Drive to France Avenue)
Next: Milestone 6 — Cornelia Drive intersection substantially complete & open to traffic · 8/21/2026 (24 days overdue)
0 done1 overdue0 on track2 not reviewed
$3,435,639
Brainerd
2026 SE Reconstruction Project
Next: 17th St SE utilities done & restored to gravel (Norwood St to Oak St) · 8/28/2026 (17 days overdue)
0 done1 overdue0 on track2 not reviewed
$2,990,000
Fergus Falls · #1159
Douglas Avenue Improvements
Next: Milestone 1 — all work except final wearing course · 10/31/2026 (in 47 days)
0 done0 on track3 not reviewed
PM Troy Ouverson / Orry Wiechmann · $1,401,096
Detroit Lakes
City of Detroit Lakes
Contract dates not loaded yet — upload the Agreement/Special Provisions.
PM Troy Ouverson / Orry Wiechmann · $690,000
Eden Prairie
Dell Road Improvement Project
Next: Milestone 1 — Phases 1 & 2 complete · 6/15/2027 (in 274 days)
0 done0 on track12 not reviewed
No contract dates loaded yet: Prior Lake, Brooklyn Center, Detroit Lakes — upload the Agreement / Special Provisions and they will be added.
Recent changes
- 9/14/26, 2:59 PMClaude verify deleted job E2E Test Job
- 9/14/26, 2:59 PMClaude verify deleted Rolling rule — E2E Test Job
- 9/14/26, 2:59 PMClaude verify marked Substantial Completion — all work not reviewed — Henning
- 9/14/26, 2:59 PMClaude verify (seed) loaded the bundled contract dates (v1: 10 jobs, 48 milestones)
- 9/14/26, 2:59 PMClaude verify marked Substantial Completion — all work off track — Henning · “e2e note”
- 9/14/26, 2:59 PMClaude verify marked Phase A complete on 10/10/2026 — E2E Test Job
- 9/14/26, 2:59 PMClaude verify edited Substantial Completion (rev) — E2E Test Job
- 9/14/26, 2:59 PMClaude verify reopened Substantial Completion — E2E Test Job
- 9/14/26, 2:59 PMClaude verify marked Substantial Completion complete on 9/14/2026 — E2E Test Job
- 9/14/26, 2:59 PMClaude verify marked Past one complete on 9/5/2026 — E2E Test Job
- 9/14/26, 2:59 PMClaude verify marked Past one on track — E2E Test Job
- 9/14/26, 2:59 PMClaude verify marked Substantial Completion off track — E2E Test Job · “waiting on Xcel”