Edina · Job #1161
Agreement dated 5/5/2026 (Contract ENG 26-7), $3,435,639.00. Substantial completion for streets = traffic devices, wear course and restoration complete, inspections no longer required. Milestones 1–3 are rolling durations; Milestone 4 (wear course in one operation) and Milestone 5 (France Ave per Hennepin County permit #2026-U0360 — 10 days' email notice to douglas.heidemann@hennepin.us before closing a County road; NB lanes reopened before SB closed) are rules. LDs per MnDOT Table 1807.1-1 (~$2,500/day in the $2M–$5M bracket — verify against the printed 2025 table). Separate LDs in the specs: $3,500/week and $500/day items in the turf/restoration sections.
Source: 1161 Edina contracts (Agreement 5/5/2026); 042726 Edina bid documents — Agreement ¶5 Completion Dates; Special Provisions 5.25
Timeline
as of Mon, Sep 14Overdue · LDs per MnDOT 1807 Table 1807.1-1Substantial CompletionOct 31, 2026Substantial CompletionDue Oct 31, 2026 · in 47 days
Not reviewed · LDs per MnDOT 1807 Table 1807.1-1 (~$2,500/day, verify)Ready for final paymentMay 31, 2027Ready for final paymentDue May 31, 2027 · in 259 days
Not reviewed · LDs per MnDOT 1807 Table 1807.1-1
Milestones
Sign in as the office to update status| Milestone | Due | At stake | Status |
|---|---|---|---|
| Contract milestones | |||
Milestone 6 — Cornelia Drive intersection substantially complete & open to traffic Work in the Cornelia Drive intersection substantially complete and open to traffic no later than August 21, 2026. Source: Agreement ¶5 Milestone 6 | 8/21/202624 days overdue | LDs per MnDOT 1807 Table 1807.1-1 | Overdue |
Substantial Completion For streets: construction-related traffic devices, bituminous wear course and restoration complete, ongoing inspections no longer required. Source: Agreement ¶5 Completion Dates; Special Provisions 5.25 | 10/31/2026in 47 days | LDs per MnDOT 1807 Table 1807.1-1 (~$2,500/day, verify) | Not reviewed |
Ready for final payment Completed and ready for final payment by May 31, 2027. Source: Agreement ¶5 Completion Dates | 5/31/2027in 259 days | LDs per MnDOT 1807 Table 1807.1-1 | Not reviewed |
| Rolling rules (no fixed date) | |||
Milestone 1 — underground utilities, grading/excavation and aggregate base within 45 days of starting construction Rolling rule Upon initiation of construction activity (temporary traffic control, start of removals, or whatever the Engineer identifies), all underground utility construction, roadway grading and excavation, and roadway aggregate base must be complete within 45 calendar days. Add a dated milestone once construction starts. Source: Agreement ¶5 Milestone 1 | rolling | — | — |
Milestone 2 — curb & gutter, concrete driveways, non-wear within 14 days of aggregate base (each segment) Rolling rule Within 14 calendar days of aggregate base installation on that segment. Source: Agreement ¶5 Milestone 2 | rolling | — | — |
Milestone 3 — bituminous driveways, sidewalk and turf restoration within 21 days of non-wear on all segments Rolling rule Within 21 calendar days of bituminous non-wear installation on all segments. Source: Agreement ¶5 Milestone 3 | rolling | — | — |
Milestone 4 — wear course for the entire project in one operation Rolling rule Source: Agreement ¶5 Milestone 4 | rolling | — | — |
Milestone 5 — France Ave work per Hennepin County permit (10-day notice before any County road closure) Rolling rule Comply with Hennepin County Utility/Obstruction Permit #2026-U0360 (UID #100025). Email douglas.heidemann@hennepin.us at least 10 days before closing a County roadway with closure/reopening dates, detour plan and a public contact. Southbound lanes stay open while northbound work is done; northbound reopened before southbound closes. Source: Agreement ¶5 Milestone 5 | rolling | — | — |