RYAN CONTRACTINGMilestones

← All jobs

Brooklyn Park · Job #1165

Wellhouse No. 11 Raw Watermain Extension — City Project No. 3007 (CIP 3007)
Owner
City of Brooklyn Park
Engineer
WSB · 033769-000
Contract
$2,547,320
Not reviewed0/6 complete · 6 not reviewed

Source: Added from the Job Tracker

Timeline

as of Sun, Nov 15
Job
Nov 2026
Dec
Jan 2027
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Brooklyn Park
Castrejon HDD quote expires (90 d…Dec 28, 2026Castrejon HDD quote expires (90 days from 9/29/2026) — subcontract neededDue Dec 28, 2026 · in 43 days
Not reviewed
Insurance renewal certificate to …Feb 10, 2027Insurance renewal certificate to City of Brooklyn Park (policies expire 2/17/2027)Due Feb 10, 2027 · in 87 days
Not reviewed
Substantial CompletionJun 30, 2027Substantial CompletionDue Jun 30, 2027 · in 227 days
Not reviewed
Final CompletionAug 30, 2027Final CompletionDue Aug 30, 2027 · in 288 days
Not reviewed

Milestones

Sign in as the office to update status
MilestoneDueAt stakeStatus
Contract milestones
Castrejon HDD quote expires (90 days from 9/29/2026) — subcontract needed
No subcontract on file for the $705,918 drilling quote.
Source: Added in the Job Tracker
12/28/2026in 43 days—Not reviewed
Insurance renewal certificate to City of Brooklyn Park (policies expire 2/17/2027)
GL/auto/umbrella/WC on the 10/19/26 COI all expire 2/17/2027. Completed-ops AI must continue 2 years after completion.
Source: Added in the Job Tracker
2/10/2027in 87 days—Not reviewed
Substantial Completion
GR-29.B: utilities, bituminous, sidewalk, pedestrian ramps, restoration and cleanup. LDs per MnDOT 1807 (rate not stated in the manual; bond request assumed $1,000/day).
Source: Job Tracker (contract dates)
Updated by Claude for Andy · 11/2/26, 9:00 AM
6/30/2027in 227 days—Not reviewed
Final Completion
GR-29.B: ready for final payment; punch list, settled curb/street repairs. Final payment needs IC-134s from all subs + lien waivers + notarized certificate; retainage released 30 days after acceptance.
Source: Job Tracker (contract dates)
Updated by Claude for Andy · 11/2/26, 9:00 AM
8/30/2027in 288 days—Not reviewed
Phases & work windows
Spring segments (Maplebrook, W Broadway, College Pkwy) — after load restrictions lift
Phase / window
GR-2.5. Leaves ~6 weeks to 6/30 substantial completion incl. paving, walk, ramps and restoration.
Source: Added in the Job Tracker
5/15/2027in 181 days—Not reviewed
Tessman Pkwy → STA 45+00 drill released (DNR Public Waters permit + Shingle Creek no-loss approval)
Phase / window
Both applications submitted by the City 8/31/2026. ~1,440 LF of the 24" HDPE drill is held until both are issued. Record the approval dates here.
Source: Added in the Job Tracker
—Not reviewed
No-work windows / restrictions
Tree felling window closes (NLEB) — all clearing done by 4/14/2027
Restriction
GR-23: tree felling only Nov 1–Apr 14. Spring-segment trees (Maplebrook, W Broadway, College Pkwy) must be down by this date or they wait until Nov 2027.
Source: Added in the Job Tracker
4/14/2027in 150 days——
Rolling rules (no fixed date)
No-LD window Nov 15 – Apr 15 (GC 3.24) — confirm with WSB
Rolling rule
GC 3.24 cites MnDOT 1806.4, which GR-29 deletes. Get written confirmation at pre-con that LDs are not assessed Nov 15–Apr 15 and what the MnDOT 1807 daily rate is.
Source: Added in the Job Tracker
rolling——

Recent changes on this job

  • 11/2/26, 9:00 AMClaude for Andy edited (Job Tracker) — Brooklyn Park
  • 11/2/26, 9:00 AMClaude for Andy edited (Job Tracker) — Brooklyn Park
  • 11/2/26, 9:00 AMClaude for Andy added (Job Tracker) — Brooklyn Park
  • 11/2/26, 9:00 AMClaude for Andy added (Job Tracker) — Brooklyn Park
  • 11/2/26, 9:00 AMClaude for Andy added (Job Tracker) — Brooklyn Park
  • 11/2/26, 9:00 AMClaude for Andy added (Job Tracker) — Brooklyn Park
  • 11/2/26, 9:00 AMClaude for Andy added (Job Tracker) — Brooklyn Park
  • 11/2/26, 9:00 AMClaude for Andy added (Job Tracker) — Brooklyn Park
  • 11/2/26, 8:52 AMClaude for Andy added (Job Tracker) — Brooklyn Park
  • 11/2/26, 8:52 AMClaude for Andy added (Job Tracker) — Brooklyn Park