Fergus Falls · Job #1159

Douglas Avenue Improvements
Owner
City of Fergus Falls
Engineer
Moore Engineering, Inc. (Kyle Meyer, PE) · 30779
RCC PM
Troy Ouverson / Orry Wiechmann
Contract
$1,401,096
Region
Outstate – West
Not reviewed0/3 complete · 3 not reviewed

Agreement effective 4/6/2026; Notice to Proceed not in the file. 2026 work wrapping (black dirt down, sod pending); wear course returns spring 2027. LDs are not additive or concurrent. Insurance certificates expire 2/17/2027 — renewals needed before 2027 work.

Source: Agreement (EJCDC C-520) Art. 4; project file notes 9/2026

Timeline

as of Mon, Sep 14
Job
Sep 2026
Oct
Nov
Dec
Jan 2027
Feb
Mar
Apr
May
Jun
Jul
Aug
Fergus Falls
Milestone 1 — all work except fin…Oct 31, 2026Milestone 1 — all work except final wearing courseDue Oct 31, 2026 · in 47 days
Not reviewed · $1,000/day LD
Substantial CompletionJun 1, 2027Substantial CompletionDue Jun 1, 2027 · in 260 days
Not reviewed · $1,200/day LD
Ready for final paymentJul 1, 2027Ready for final paymentDue Jul 1, 2027 · in 290 days
Not reviewed · $1,200/day LD

Milestones

Sign in as the office to update status
MilestoneDueAt stakeStatus
Contract milestones
Milestone 1 — all work except final wearing course
Everything but the final wearing course (wear course returns spring 2027).
Source: Agreement Art. 4
10/31/2026in 47 days$1,000/day LDNot reviewed
Substantial Completion
Retainage released no later than 60 days after substantial completion (needs surety consent).
Source: Agreement Art. 4
6/1/2027in 260 days$1,200/day LDNot reviewed
Ready for final payment
LDs are not additive or concurrent.
Source: Agreement Art. 4
7/1/2027in 290 days$1,200/day LDNot reviewed

Recent changes on this job

No changes yet.