Fergus Falls · Job #1159
Douglas Avenue Improvements
Overdue0/3 complete · 1 overdue · 2 not reviewed
Agreement effective 4/6/2026; Notice to Proceed not in the file. 2026 work wrapping (black dirt down, sod pending); wear course returns spring 2027. LDs are not additive or concurrent. Insurance certificates expire 2/17/2027 — renewals needed before 2027 work.
Source: Agreement (EJCDC C-520) Art. 4; project file notes 9/2026
Timeline
as of Sun, Nov 15Job
Oct 2026
Nov
Dec
Jan 2027
Feb
Mar
Apr
May
Jun
Jul
Aug
Fergus Falls
Milestone 1 — all work except fin…Oct 31, 2026Milestone 1 — all work except final wearing courseDue Oct 31, 2026 · 15 days ago
Overdue · $1,000/day LDSubstantial CompletionJun 1, 2027Substantial CompletionDue Jun 1, 2027 · in 198 days
Not reviewed · $1,200/day LDReady for final paymentJul 1, 2027Ready for final paymentDue Jul 1, 2027 · in 228 days
Not reviewed · $1,200/day LD
Overdue · $1,000/day LDSubstantial CompletionJun 1, 2027Substantial CompletionDue Jun 1, 2027 · in 198 days
Not reviewed · $1,200/day LDReady for final paymentJul 1, 2027Ready for final paymentDue Jul 1, 2027 · in 228 days
Not reviewed · $1,200/day LD
Milestones
Sign in as the office to update status| Milestone | Due | At stake | Status |
|---|---|---|---|
| Contract milestones | |||
Milestone 1 — all work except final wearing course Everything but the final wearing course (wear course returns spring 2027). Source: Agreement Art. 4 | 10/31/202615 days overdue | $1,000/day LD | Overdue |
Substantial Completion Retainage released no later than 60 days after substantial completion (needs surety consent). Source: Agreement Art. 4 | 6/1/2027in 198 days | $1,200/day LD | Not reviewed |
Ready for final payment LDs are not additive or concurrent. Source: Agreement Art. 4 | 7/1/2027in 228 days | $1,200/day LD | Not reviewed |
Recent changes on this job
No changes yet.