Moorhead · Job #1157
Partridge Creek Addition Street & Utility Improvements, Stormwater Pond and 28th St S Improvements
Overdue0/3 complete · 1 overdue · 2 not reviewed
Completion dates set by Addendum No. 2 (3/6/2026). LDs per MnDOT 1807 Table 1807.1-1 — $2,500/calendar day at this contract size. "Substantially complete" is not defined in the contract; see the 8/18/2026 internal memo and letter to the City. RCC's own bid-time work schedule (Form of Contract 00500-4): grading 4/27–7/6, sanitary/water 4/27–6/15, storm 4/27–6/29, concrete 7/13–7/27, paving 8/10–8/21, seeding 9/14–10/1.
Source: Fully executed contract (Special Provision 11 as amended by Addendum No. 2); Notice to Proceed 4/15/2026; Form of Contract 00500-4 work schedule
Timeline
as of Mon, Sep 14Job
Sep 2026
Oct
Nov
Moorhead
28th St S + Partridge Creek utili…Sep 1, 202628th St S + Partridge Creek utilities & street substantially completeDue Sep 1, 2026 · 13 days ago
Overdue · $2,500/day LD · per MnDOT 1807 Table 1807.1-1All other remaining work substant…Oct 1, 2026All other remaining work substantially completeDue Oct 1, 2026 · in 17 days
Not reviewed · $2,500/day LD · per MnDOT 1807 Table 1807.1-1Fully complete — turf established…Oct 15, 2026Fully complete — turf established, punch list closedDue Oct 15, 2026 · in 31 days
Not reviewed · $2,500/day LD · per MnDOT 1807 Table 1807.1-1
Overdue · $2,500/day LD · per MnDOT 1807 Table 1807.1-1All other remaining work substant…Oct 1, 2026All other remaining work substantially completeDue Oct 1, 2026 · in 17 days
Not reviewed · $2,500/day LD · per MnDOT 1807 Table 1807.1-1Fully complete — turf established…Oct 15, 2026Fully complete — turf established, punch list closedDue Oct 15, 2026 · in 31 days
Not reviewed · $2,500/day LD · per MnDOT 1807 Table 1807.1-1
Milestones
Sign in as the office to update status| Milestone | Due | At stake | Status |
|---|---|---|---|
| Contract milestones | |||
28th St S + Partridge Creek utilities & street substantially complete All utility and street construction (incl. pavement and curb & gutter) on 28th Street South and within Partridge Creek Addition. Excludes topsoil placement, boulevard grading and turf establishment. Date moved from 8/1 by Addendum No. 2. RCC wrote to the City 8/18/2026 asking for written confirmation of the milestone scope (sidewalk/ramps held for MPS/Xcel dry-utility work). Source: Special Provision 11 as amended by Addendum No. 2 §I.A | 9/1/2026was 8/1/202613 days overdue | $2,500/day LD · per MnDOT 1807 Table 1807.1-1 | Overdue |
All other remaining work substantially complete Everything outside the 9/1 milestone scope. Date moved from 9/1 by Addendum No. 2. Source: Special Provision 11 as amended by Addendum No. 2 §I.A | 10/1/2026was 9/1/2026in 17 days | $2,500/day LD · per MnDOT 1807 Table 1807.1-1 | Not reviewed due in 17 days |
Fully complete — turf established, punch list closed All work including establishment of turf and punch-list items. Date moved from 9/30 by Addendum No. 2. Source: Special Provision 11 as amended by Addendum No. 2 §I.A | 10/15/2026was 9/30/2026in 31 days | $2,500/day LD · per MnDOT 1807 Table 1807.1-1 | Not reviewed |
Recent changes on this job
No changes yet.