Henning · Job #1162

2026 Utility & Surface Improvements
Owner
City of Henning
Engineer
Apex Engineering Group (Sam Ruppert, PE) · 24.200.0214
RCC PM
Troy Ouverson
Contract
$6,662,565
Contract times run from
9/8/2026
Region
Outstate – West
Overdue0/5 complete · 2 overdue · 3 not reviewed

PFA-funded (CWRF/DWRF). Contract price $6,662,565.45 after Change Order No. 1 (8/19/2026, Alts 1 and 3 removed). Notice to Proceed issued 9/8/2026 with Contract Times running from that date. The 2026 phase milestones on the phasing plan pre-date the NTP — a written re-baseline is needed (June 24 letter to Apex proposed a single-season 2027 start).

Source: Notice to Proceed 9/8/2026; Agreement Art. 4 (043026 Henning spec book); Plans Sheet 3 phasing notes

Timeline

as of Sun, Nov 15
Job
Aug 2026
Oct
Jan 2027
Apr
Jul
Oct
Jan 2028
Apr
Jul
Henning
No work in Phase 7 area (Sep–Nov)
No work in Phase 7 area (Apr–May)
No work in Phase 7 area (Sep–Nov)
Phase 1 area substantially comple…Aug 31, 2026Phase 1 area substantially completeDue Aug 31, 2026 · 76 days ago
Overdue · $2,500/day LD
Phase 2 area substantially comple…Oct 30, 2026Phase 2 area substantially completeDue Oct 30, 2026 · 16 days ago
Overdue · $2,500/day LD
All water distribution work incl.…Aug 1, 2027All water distribution work incl. testing completeDue Aug 1, 2027 · in 259 days
Not reviewed · $2,500/day LD
Substantial Completion — all workOct 30, 2027Substantial Completion — all workDue Oct 30, 2027 · in 349 days
Not reviewed · $2,500/day LD
Ready for final paymentJun 16, 2028Ready for final paymentDue Jun 16, 2028 · in 579 days
Not reviewed · $1,250/day LD

Milestones

Sign in as the office to update status
MilestoneDueAt stakeStatus
Contract milestones
Phase 1 area substantially complete
Contract milestone from the phasing plan; milestone LDs are additive to substantial-completion LDs. The Notice to Proceed was not issued until 9/8/2026, so this date needs a written re-baseline or change order — the 6/24/2026 letter to Apex proposed a single-season 2027 start.
Source: Plans Sheet 3 note 5; Agreement ¶4.03.A.4
8/31/202676 days overdue$2,500/day LDOverdue
Phase 2 area substantially complete
Contract milestone from the phasing plan; see Phase 1 — same re-baseline issue after the 9/8/2026 NTP.
Source: Plans Sheet 3 note 6; Agreement ¶4.03.A.4
10/30/202616 days overdue$2,500/day LDOverdue
All water distribution work incl. testing complete
All underground utility work relating to the City's water distribution system, including testing, unless approved by the Engineer in writing.
Source: Plans Sheet 3 note 8; Agreement ¶4.03.A.4
8/1/2027in 259 days$2,500/day LDNot reviewed
Substantial Completion — all work
Excludes wear course pavement, final casting adjustments, pavement markings and final turf maintenance. Not concurrent with final-completion LDs.
Source: Notice to Proceed 9/8/2026; Agreement ¶4.02–4.03; Plans Sheet 3 note 1
Updated by Claude verify · 9/14/26, 2:59 PM
10/30/2027in 349 days$2,500/day LDNot reviewed
Ready for final payment
Final completion incl. wear course, castings, markings, turf. Needs IC-134s from every sub, NPDES NOT, certified payrolls, warranties.
Source: Notice to Proceed 9/8/2026; Agreement ¶4.03.A.2
6/16/2028in 579 days$1,250/day LDNot reviewed
No-work windows / restrictions
No work in Phase 7 area (Sep–Nov)
Restriction
No work in the Phase 7 area in April, May, September, October or November unless approved by the Engineer in writing.
Source: Plans Sheet 3 note 7
9/1/2026 – 11/30/2026in 15 days——
No work in Phase 7 area (Apr–May)
Restriction
No work in the Phase 7 area in April, May, September, October or November unless approved by the Engineer in writing.
Source: Plans Sheet 3 note 7
4/1/2027 – 5/31/2027in 197 days——
Henning Festival — Balmoral Ave + roads S/W of TH 108 open
Restriction
Balmoral Avenue and all roads south and west of Douglas Ave (TH 108) must be open for the festival. 2026 festival was July 10–12; exact 2027 dates not set — placeholder for the second weekend of July, confirm with the City.
Source: Plans Sheet 3 note 9
7/9/2027 – 7/11/2027in 238 days——
No work in Phase 7 area (Sep–Nov)
Restriction
No work in the Phase 7 area in April, May, September, October or November unless approved by the Engineer in writing.
Source: Plans Sheet 3 note 7
9/1/2027 – 11/30/2027in 380 days——
Rolling rules (no fixed date)
One phase at a time
Rolling rule
Construction may not start in a second phase area until the previous phase is substantially complete, unless approved by the Engineer in writing. Vehicle access to adjacent properties restored each night.
Source: Plans Sheet 3 note 4
rolling——

Recent changes on this job

  • 9/14/26, 2:59 PMClaude verify marked Substantial Completion — all work not reviewed — Henning
  • 9/14/26, 2:59 PMClaude verify marked Substantial Completion — all work off track — Henning · “e2e note”