Henning · Job #1162

2026 Utility & Surface Improvements
Owner
City of Henning
Engineer
Apex Engineering Group (Sam Ruppert, PE) · 24.200.0214
RCC PM
Troy Ouverson
Contract
$6,662,565
Contract times run from
9/8/2026
Region
Outstate – West
Overdue0/5 complete · 1 overdue · 4 not reviewed

PFA-funded (CWRF/DWRF). Contract price $6,662,565.45 after Change Order No. 1 (8/19/2026, Alts 1 and 3 removed). Notice to Proceed issued 9/8/2026 with Contract Times running from that date. The 2026 phase milestones on the phasing plan pre-date the NTP — a written re-baseline is needed (June 24 letter to Apex proposed a single-season 2027 start).

Source: Notice to Proceed 9/8/2026; Agreement Art. 4 (043026 Henning spec book); Plans Sheet 3 phasing notes

Timeline

as of Mon, Sep 14
Job
Aug 2026
Oct
Jan 2027
Apr
Jul
Oct
Jan 2028
Apr
Jul
Henning
No work in Phase 7 area (Sep–Nov)
No work in Phase 7 area (Apr–May)
No work in Phase 7 area (Sep–Nov)
Phase 1 area substantially comple…Aug 31, 2026Phase 1 area substantially completeDue Aug 31, 2026 · 14 days ago
Overdue · $2,500/day LD
Phase 2 area substantially comple…Oct 30, 2026Phase 2 area substantially completeDue Oct 30, 2026 · in 46 days
Not reviewed · $2,500/day LD
All water distribution work incl.…Aug 1, 2027All water distribution work incl. testing completeDue Aug 1, 2027 · in 321 days
Not reviewed · $2,500/day LD
Substantial Completion — all workOct 30, 2027Substantial Completion — all workDue Oct 30, 2027 · in 411 days
Not reviewed · $2,500/day LD
Ready for final paymentJun 16, 2028Ready for final paymentDue Jun 16, 2028 · in 641 days
Not reviewed · $1,250/day LD

Milestones

Sign in as the office to update status
MilestoneDueAt stakeStatus
Contract milestones
Phase 1 area substantially complete
Contract milestone from the phasing plan; milestone LDs are additive to substantial-completion LDs. The Notice to Proceed was not issued until 9/8/2026, so this date needs a written re-baseline or change order — the 6/24/2026 letter to Apex proposed a single-season 2027 start.
Source: Plans Sheet 3 note 5; Agreement ¶4.03.A.4
8/31/202614 days overdue$2,500/day LDOverdue
Phase 2 area substantially complete
Contract milestone from the phasing plan; see Phase 1 — same re-baseline issue after the 9/8/2026 NTP.
Source: Plans Sheet 3 note 6; Agreement ¶4.03.A.4
10/30/2026in 46 days$2,500/day LDNot reviewed
All water distribution work incl. testing complete
All underground utility work relating to the City's water distribution system, including testing, unless approved by the Engineer in writing.
Source: Plans Sheet 3 note 8; Agreement ¶4.03.A.4
8/1/2027in 321 days$2,500/day LDNot reviewed
Substantial Completion — all work
Excludes wear course pavement, final casting adjustments, pavement markings and final turf maintenance. Not concurrent with final-completion LDs.
Source: Notice to Proceed 9/8/2026; Agreement ¶4.02–4.03; Plans Sheet 3 note 1
Updated by Claude verify · 9/14/26, 2:59 PM
10/30/2027in 411 days$2,500/day LDNot reviewed
Ready for final payment
Final completion incl. wear course, castings, markings, turf. Needs IC-134s from every sub, NPDES NOT, certified payrolls, warranties.
Source: Notice to Proceed 9/8/2026; Agreement ¶4.03.A.2
6/16/2028in 641 days$1,250/day LDNot reviewed
No-work windows / restrictions
No work in Phase 7 area (Sep–Nov)
Restriction
No work in the Phase 7 area in April, May, September, October or November unless approved by the Engineer in writing.
Source: Plans Sheet 3 note 7
9/1/202611/30/2026in 77 days
No work in Phase 7 area (Apr–May)
Restriction
No work in the Phase 7 area in April, May, September, October or November unless approved by the Engineer in writing.
Source: Plans Sheet 3 note 7
4/1/20275/31/2027in 259 days
Henning Festival — Balmoral Ave + roads S/W of TH 108 open
Restriction
Balmoral Avenue and all roads south and west of Douglas Ave (TH 108) must be open for the festival. 2026 festival was July 10–12; exact 2027 dates not set — placeholder for the second weekend of July, confirm with the City.
Source: Plans Sheet 3 note 9
7/9/20277/11/2027in 300 days
No work in Phase 7 area (Sep–Nov)
Restriction
No work in the Phase 7 area in April, May, September, October or November unless approved by the Engineer in writing.
Source: Plans Sheet 3 note 7
9/1/202711/30/2027in 442 days
Rolling rules (no fixed date)
One phase at a time
Rolling rule
Construction may not start in a second phase area until the previous phase is substantially complete, unless approved by the Engineer in writing. Vehicle access to adjacent properties restored each night.
Source: Plans Sheet 3 note 4
rolling

Recent changes on this job

  • 9/14/26, 2:59 PMClaude verify marked Substantial Completion — all work not reviewedHenning
  • 9/14/26, 2:59 PMClaude verify marked Substantial Completion — all work off trackHenning · “e2e note