Eden Prairie

Dell Road Improvement Project
Owner
City of Eden Prairie
Engineer
WSB (Jupe Hale, PE) · 010336-000 (City Project 17-5990 · S.A.P. 181-113-006)
Region
7-County Metro
Not reviewed0/12 complete · 12 not reviewed

Bid 8/20/2026 — award status to confirm; deactivate this job if it was not awarded. Notice to Proceed anticipated September 2026, start within 7 days of NTP. $60,000 total incentive, paid only after substantial completion of ALL phases. Site-cleanliness LDs $250/day/area after first warning. Working hours 7 AM–7 PM Mon–Fri.

Source: Eden Prairie project manual + Addenda 1–2 (Special Conditions; Construction Staging Plan Sheet 25); Eden_Prairie_Dell_Road_Milestone_Schedule.xlsx (8/20/2026)

Timeline

as of Mon, Sep 14
Job
Sep 2026
Oct
Jan 2027
Apr
Jul
Oct
Jan 2028
Apr
Jul
Eden Prairie
Phase 1
Tree clearing & grubbing window (all clearing happens here)
Phase 2
Riley Creek box culvert — winter window
No in-stream work — Riley Creek
Phase 3
Phase 4
Phase 5
Phase 6 — trail paving, wear course, punch list
Milestone 1 — Phases 1 & 2 comple…Jun 15, 2027Milestone 1 — Phases 1 & 2 completeDue Jun 15, 2027 · in 274 days
Not reviewed · $20,000 incentive
Milestone 2 — Phases 3, 4 & 5 com…Nov 15, 2027Milestone 2 — Phases 3, 4 & 5 completeDue Nov 15, 2027 · in 427 days
Not reviewed · $40,000 incentive
Substantial completionDec 1, 2027Substantial completionDue Dec 1, 2027 · in 443 days
Not reviewed
Final paymentJul 1, 2028Final paymentDue Jul 1, 2028 · in 656 days
Not reviewed

Milestones

Sign in as the office to update status
MilestoneDueAt stakeStatus
Contract milestones
Milestone 1 — Phases 1 & 2 complete
Conflict to resolve with WSB: the Staging Plan runs Phase 2 to 7/15/2027; Special Conditions govern (SC 2-05). Incentive paid only after substantial completion of all phases.
Source: Special Conditions — milestones/incentives
6/15/2027in 274 days$20,000 incentiveNot reviewed
Milestone 2 — Phases 3, 4 & 5 complete
Incentive bullet says 12/1/2027 — conflict raised with WSB.
Source: Special Conditions — milestones/incentives
11/15/2027in 427 days$40,000 incentiveNot reviewed
Substantial completion
Site-cleanliness LDs $250/day/area after first warning apply throughout.
Source: Special Conditions
12/1/2027in 443 daysNot reviewed
Final payment
Source: Special Conditions
7/1/2028in 656 daysNot reviewed
Phases & work windows
Phase 1
Phase / window
Source: Construction Staging Plan, Sheet 25
10/1/202611/30/2026in 77 daysNot reviewed
Riley Creek box culvert — winter window
Phase / window
10x8 precast box culvert (Bridge 27J93) must go in before the in-stream restriction starts 3/15. Temporary stream diversion capped at 6 months (USACE permit).
Source: Permits; Special Conditions
12/1/20263/14/2027in 181 daysNot reviewed
Tree clearing & grubbing window (all clearing happens here)
Phase / window
After Oct 31, 2026 for Phase 1/2 areas; before Apr 15, 2027 for Phase 3/4 areas.
Source: Special Conditions / permits
11/1/20264/15/2027in 213 daysNot reviewed
Phase 2
Phase / window
Source: Construction Staging Plan, Sheet 25
12/1/20267/15/2027in 304 daysNot reviewed
Phase 3
Phase / window
Source: Construction Staging Plan, Sheet 25
7/16/20278/15/2027in 335 daysNot reviewed
Phase 4
Phase / window
Source: Construction Staging Plan, Sheet 25
8/16/202710/15/2027in 396 daysNot reviewed
Phase 5
Phase / window
Source: Construction Staging Plan, Sheet 25
10/16/202712/1/2027in 443 daysNot reviewed
Phase 6 — trail paving, wear course, punch list
Phase / window
Source: Construction Staging Plan, Sheet 25
5/1/20287/31/2028in 686 daysNot reviewed
No-work windows / restrictions
No in-stream work — Riley Creek
Restriction
In-stream work on Riley Creek prohibited March 15 – June 15.
Source: Permits
3/15/20276/15/2027in 274 days
Rolling rules (no fixed date)
Temporary stream diversion limited to 6 months
Rolling rule
USACE permit condition.
Source: USACE permit
rolling

Recent changes on this job

No changes yet.